Day 554: Swimming Pool and Gym Room Near Completion
2
Day 540: Fittings in Classrooms and Bathrooms In Progress

Day 554: Swimming Pool and Gym Room Near Completion

September 27, 2016

Tiling in the swimming pool has been completed. Bricks are currently being laid to construct a wall for the pool showers. The remaining work in the swimming pool includes the sand wash floor finishing and the pool fence. The plaster work in the big gym is complete along with painting. The gym’s basketball hoops have been installed along with the light fixtures. The remaining work includes the multi-purpose flooring and installation of air-conditioners.  The intricate fence for the second floor overlooking the amphitheatre has been built along with a similar version for the second floor verandah surrounding the signature tree. The steel bridge work is now complete with a neat paint finish. Curved windows have been installed in the foyer area of the main building near the front entrance of the school. The sand wash floor in all areas of the first floor is almost complete including the foyer and the large cafeteria. Workers have also begun the process of installing kitchen equipment including the commercial exhaust hood and duct.  Lighting fixtures have been installed in all rooms now including the third floor office. Fire alarm signs, sirens and light/plug fixtures are currently being set up in each of the classrooms. Certainly a lot of progress at the new campus in the last two weeks!

  • S__87269440
  • S__87269443
  • S__87269463_0
  • S__87269461
  • S__87269464
  • S__87269403
  • S__87269406
  • S__87269449
  • S__87269437_0
  • S__87269434
  • S__87269387
  • S__87269392
  • S__87269451
  • S__87269411
  • S__87269448
  • S__87269409

Day 540: Fittings in Classrooms and Bathrooms In Progress

September 13, 2016

Interior work at the new campus site has started to move quickly especially in the classrooms and bathrooms. After bathroom floor tiling was completed, partition doors (orange and yellow) were installed in the different student and adult bathrooms. Sanitary ware including toilets and sinks were also fitted in the bathrooms. In the classrooms, light fixtures were installed in the remaining classrooms including the third floor with neat hanging fixtures. Door frames and glass windows have also been installed in the classrooms on the 1st and 2nd floors. The big gym room has now received its ceiling and plaster finish and awaits the multi-purpose flooring. The wall plastering is complete in the school bridge along with the sand wash floor finishing. Tile work has begun in the swimming pool while on the other side of the L-shaped playground the school’s signature tree stands tall and green! Temporary school signs have been placed on the fence perimeter as installation of the permanent school signs will follow soon.

  • S__83656740
  • S__83656784
  • S__83656781
  • S__83656788
  • S__83656767
  • S__83656772
  • S__83656744
  • S__83656751
  • S__83656737
  • S__83656747
  • S__83656789
  • S__83656765
  • S__83656764
  • S__83656728
  • S__83656725

Copyright © 1990-2015. Magic Years International School - IB World School.