Day 114: Precast Concrete Flooring Under Way

July 15, 2015

On day 114, concrete flooring of the ground floor was well under way. Precast concrete floor slabs were erected and put into place above the ground beams. Wire mesh was then assembled on top of the concrete slabs to cast the concrete floor topping. At the same time, columns were slowly being raised to prepare for the second floor of the buildings.